Members of the implementation team of the Project EEA 2019/107379 at Energy Forum – Sustainable Opportunities in Romania and Cooperation with Norway/Iceland, 25 April 2024, Bucharest, Romania

Members of the implementation team of the Project EEA 2019/107379 at Energy Forum – Sustainable Opportunities in Romania and Cooperation with Norway/Iceland, 25 April 2024, Bucharest, Romania

In 25 April 2024, members of the implementation team of the Project EEA 2019/107379 have attended in Bucharest Nord Events Center by Globalworth at the Energy Forum – Sustainable Opportunities in Romania and Cooperation with Norway/Iceland, in search for future opportunities of cooperation on the green transition with the partners from Norway and Iceland. Key…

Completion of the project EEA 2019/107379 „Hybrid system for energetic efficiency using geothermal energy applied in UPG Ploiesti campus”

Completion of the project EEA 2019/107379 „Hybrid system for energetic efficiency using geothermal energy applied in UPG Ploiesti campus”

Petroleum-Gas University of Ploiesti (UPG) is beneficiary of the project EEA 2019/107379 “Hybrid system for energetic efficiency using geothermal energy applied in UPG Ploiesti campus”, financed by the EEA and Norway Grants by Norwegian Financial Mechanisms 2014-2021 – “Energy Program in Romania”, Call 2 – Increased capacity for the supply of renewable energy – Geothermal…

In week 17 of 2024, in the Project EEA 107379/2019 the activities for automation system (system for command, measurement and control) (including design, execution and installing) (batch 1) were completed

In week 17 of 2024, in the Project EEA 107379/2019 the activities for automation system (system for command, measurement and control) (including design, execution and installing) (batch 1) were completed

In week 17 of 2024, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy applied in UPG Ploiesti campus) it has been completed the contract for supplying/design/execution/installing of the automation system (system for command, measurement and control) (including design, execution and installing) and his reception took place. The contract goals were…

In week 16 of 2024 in the Project EEA 107379/2019 the activities for “Thermic installations (including design, execution and installation of heat pumps and auxiliary equipment)” were completed

In week 16 of 2024 in the Project EEA 107379/2019 the activities for “Thermic installations (including design, execution and installation of heat pumps and auxiliary equipment)” were completed

In week 16 of 2024, in the Grant EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus) it has been completed the contract for supplying/design/execution/installing of the “Thermic installations (including design, execution and installation of heat pumps and auxiliary equipment)”. The goals of the contract were represented by eight…

In week 15 of 2024, in the Project EEA 107379/2019 the activities for installations of electrical power supply (including design, execution and installing) (batch 2) were completed

In week 15 of 2024, in the Project EEA 107379/2019 the activities for installations of electrical power supply (including design, execution and installing) (batch 2) were completed

In week 15 of 2024, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus) it has been completed the contract for supplying/design/execution/installing of the power supply electrical installation in C building and thermal power plant (including design, execution and installing) and his reception took place. The…

In week 12 of 2024, in the Project EEA 107379/2019 the main thermic equipment (HEAT PUMPS) were delivered in Ploiesti

In week 12 of 2024, in the Project EEA 107379/2019 the main thermic equipment (HEAT PUMPS) were delivered in Ploiesti

The investment is part of the grant EEA 107379/2019 “Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus”, financed by the EEA and Norway Grants by Norwegian Financial Mechanisms 2014-2021 – “Energy Program in Romania”, Call 2 – Increased capacity for the supply of renewable energy – Geothermal energy.

Thermal installations (fan convectors and auxiliary equipment, interior installation and insulation works) were completed

In week 9 of 2024, in the Project EEA 107379/2019 the activities for “Thermal installations (fan convectors and auxiliary equipment, interior installation and insulation works)” were completed In week 9 of 2024, in the Grant EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus) it has been completed the…

Electrical power supply installations, command, measurement and control system (building E, building C and the thermal power plant) (including design, execution and installation).

In week 47 of 2023, in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy applied in UPG Ploiesti campus) it was launched the public acquisition procedure SEAP for “Electrical power supply installations, command, measurement and control system (building E, building C and the thermal power plant) (including design, execution and installation)….

Workshop on “Hybrid System for Energetic Efficiency using Geothermal Energy, Applied in UPG Campus in Ploiesti”

Dear guests, The Petroleum-Gas University of Ploiesti (UPG) is pleased to announce an upcoming workshop in collaboration with Innovation Norway and the District  Council of Prahova of the project “Hybrid System for Energetic Efficiency using Geothermal Energy, Applied in UPG Campus in Ploiesti”. This workshop is a result of an exciting partnership between UPG and…

In week 27 of 2023, in the Project EEA 107379/2019 the activities for “Recovery energy system from thermal plant CT1” were completed

In week 27 of 2023, in the Project EEA 107379/2019 the activities for “Recovery energy system from thermal plant CT1” were completed

In week 27 of 2023, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) it has been completed the contract for supplying/design/execution/installing of the “Recovery energy system from thermal plant CT1” and his reception took place. The contract goals were represented by three activities as follows: Cod CPV:…