Thermal installations (including designing, execution and installing heat pumps and accessories)

In week 23 of 2023, in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) it was launched the public acquisition procedure SEAP for “Thermal installations (including designing, execution and installing heat pumps and accessories)”. The goals of public acquisition procedure SEAP launched are represented by eight activities as…

In week 16 of 2023, in the EEA Grant 107379/2019 the activities for “Groundworks and buried installation” were finished

In week 16 of 2023, in the EEA Grant 107379/2019 the activities for “Groundworks and buried installation” were finished

In week 16 of 2023 in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, it has been completed the contract for supplying/design/execution/installing of electric and hydronic external networks (“Groundworks and buried installations”) and his reception took place. The investment is part of the grant “Hybrid system for energetic efficiency using geothermal…

Thermal installations (purchase of 25 m3 water buffers, 3-way valves and automatic balancing valves, convectors and auxiliary equipment, convector works and interior installations, interior pipes (additional), interior installation and insulation works)

In week 19 of 2023, in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) it was launched the public acquisition procedure SEAP for “Thermal installations (purchase of 25 m3 water buffers, 3-way valves and automatic balancing valves, convectors and auxiliary equipment, convector works and interior installations, interior pipes…

“Recovery energy system from thermal plant CT1”

In week 13 of 2023, in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) it was completed the SEAP public tender (SCN1120407/13.02.2023) and was signed the contract with the winner of the tender for the execution “Recovery energy system from thermal plant CT1”. The execution period for this…

In week 8 of 2023, in the EEA Grant 107379/2019 the “Ground heat exchanger, design, execution and installation” works were finished.

In week 8 of 2023, in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) the “Ground heat exchanger, design, execution and installation” works were finished . The contract activities were completed as follows: Activity 6.11 – Geothermal heat exchanger installation works: heat exchanger location and installation, underground installation,…

Thermal Energy Recovery System – Thermal Power Plant CT1

Thermal Energy Recovery System – Thermal Power Plant CT1

We are pleased to announce that the public acquisition for Thermal Energy Recovery System – Thermal Power Plant CT1, has been launched in week 6 of 2023, though the electronic public procurement system.This acquisition contains design/execution/procurement/setting/installation of equipment, including completing 3 activities, as follows:  Details can be found in the specifications documentation uploaded on the…

Groundworks and buried installations

Groundworks and buried installations

In week 50 of 2022 in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) the procedure for SEAP public tender (SCN1111334/22.07.2022) was finished and the contract with the winner of the tender for the execution “Groundworks and buried installations” was signed. The contract goals are represent by five…

Ground heat exchanger, design, execution and installation

Ground heat exchanger, design, execution and installation

In week 41 of 2022, in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) the procedure for SEAP public tender (SCN1111334/22.07.2022) was finished the and the contract winner of the tender for the execution was signed named “Ground heat exchanger, design, execution and installation”. The contract goals are…

“Drilling works”

“Drilling works”

Start In week 14 of 2022 in EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG), the tender winning company for contract Execution “Drilling works” took over the site and started the works. The signed contract goals were represent by four activities as follows: CPV code: 45262220-9 – Activity 3.13…

Invitation to the SME Congress in Poland and an Event on Green Technologies in Energy – Travel Grants

Invitation to the SME Congress in Poland and an Event on Green Technologies in Energy – Travel Grants

Norwegian businesses are invited to the European SME Congress in Katowice, Poland, and the event “Green Technologies for Energy Security”. SME Congress is the Europe’s largest meeting place for SMEs! The Norway Grants covers travel, accommodation and entrance with up to 2000 euro. Innovation Norway and The Polish Agency for Enterprise Development (PARP) invite Norwegian…