EFICIENTA ENERGETICĂ ÎN CLĂDIRI ȘI ENERGIA GEOTERMALĂ
Studiu de caz campus Universitatea Petrol-Gaze Ploiești (Romania)
In week 9 of 2024, in the Project EEA 107379/2019 the activities for “Thermal installations (fan convectors and auxiliary equipment, interior installation and insulation works)” were completed In week 9 of 2024, in the Grant EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus) it has been completed the…
In week 15 of 2024, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus) it has been completed the contract for supplying/design/execution/installing of the power supply electrical installation in C building and thermal power plant (including design, execution and installing) and his reception took place. The…
In May 29, 2024, at the Petroleum-Gas University of Ploiesti, Ap9 Hall, 9-12 hours, a workshop was held to promote by the Petroleum-Gas University of Ploiesti the project EEA 2019/107379 financed by EEA and Norway Grants and the Prahova County Council. In the project carried out within the Energy Programme in Romania and whose beneficiary…
In May 10, 2024, eng. Dan CÎRJAN – chief-designer and the Project Partner in the Projects EEA 2019/107379 and EEA 2024/388116, attended in the 2nd International Conference on Electrical and Power Engineering ICPE-CA – ASMES 2024, organized in Tulcea (Romania) in the 9-12 May 2024. General topics of the ASMES Conference 2024 are as follows:…
In May 29, 2024, at the Petroleum-Gas University of Ploiesti, Ap9 Hall, 15-18 hours, a workshop was held to promote by the Petroleum-Gas University of Ploiesti the project EEA 2019/107379 financed by EEA and Norway Grants and the Prahova County Council. In the project carried out within the Energy Programme in Romania and whose beneficiary…
The investment is part of the grant EEA 107379/2019 “Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus”, financed by the EEA and Norway Grants by Norwegian Financial Mechanisms 2014-2021 – “Energy Program in Romania”, Call 2 – Increased capacity for the supply of renewable energy – Geothermal energy.