In week 15 of 2024, in the Project EEA 107379/2019 the activities for installations of electrical power supply (including design, execution and installing) (batch 2) were completed
In week 15 of 2024, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus) it has been completed the contract for supplying/design/execution/installing of the power supply electrical installation in C building and thermal power plant (including design, execution and installing) and his reception took place.
The contract goal was represented by one activity as follows:
Code CPV: 31682530-4 – Activity 6.5.2 – Installations for electrical power supply (purchase of electrical power supplies)
The investment is part of the grant “Hybrid system for energetic efficiency using geothermal energy, applied in UPG”, financed by the EEA and Norwegian Financial Mechanisms 2014-2021 – “Energy Program in Romania”, Call 2 – Increased capacity for the supply of renewable energy – Geothermal energy.