EFICIENTA ENERGETICĂ ÎN CLĂDIRI ȘI ENERGIA GEOTERMALĂ
Studiu de caz campus Universitatea Petrol-Gaze Ploiești (Romania)
In week 17 of 2024, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy applied in UPG Ploiesti campus) it has been completed the contract for supplying/design/execution/installing of the automation system (system for command, measurement and control) (including design, execution and installing) and his reception took place. The contract goals were…
In week 9 of 2024, in the Project EEA 107379/2019 the activities for “Thermal installations (fan convectors and auxiliary equipment, interior installation and insulation works)” were completed In week 9 of 2024, in the Grant EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus) it has been completed the…
In week 8 of 2023, in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) the “Ground heat exchanger, design, execution and installation” works were finished . The contract activities were completed as follows: Activity 6.11 – Geothermal heat exchanger installation works: heat exchanger location and installation, underground installation,…
In week 13 of 2023, in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) it was completed the SEAP public tender (SCN1120407/13.02.2023) and was signed the contract with the winner of the tender for the execution “Recovery energy system from thermal plant CT1”. The execution period for this…
The EEA and Norway Grants Programme in Romania has opened its final call for projects: the Small Grants Scheme for the Development of Business Skills in Romania. Innovation Norway held a webinar to present the call and answer questions. See the recording and presentations of the webinar here!
In week 15 of 2024, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus) it has been completed the contract for supplying/design/execution/installing of the power supply electrical installation in C building and thermal power plant (including design, execution and installing) and his reception took place. The…