“Recovery energy system from thermal plant CT1”
In week 13 of 2023, in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) it was completed the SEAP public tender (SCN1120407/13.02.2023) and was signed the contract with the winner of the tender for the execution “Recovery energy system from thermal plant CT1”. The execution period for this contract is 3 months.
The contract activities are listed as follows:
Cod CPV: 42161000-5 – Activity 3.5 – Buffers/water tanks of 4000 liters with two coils
Cod CPV 42164000-6 – Activity 3.16 – Recovery thermic energy system (including design and installing)
Cod CPV: 45331100-7 – Activity 6.7 – Plumber works & auxiliaries in thermal plant (CT1) (buffers, recovery installation connection, circulation pumps, connections, valves)
The investment is part of the grant “Hybrid system for energetic efficiency using geothermal energy, applied in UPG”, financed by the EEA and Norwegian Financial Mechanisms 2014-2021 – “Energy Program in Romania”, Call 2 – Increased capacity for the supply of renewable energy – Geothermal energy.