In week 27 of 2023, in the Project EEA 107379/2019 the activities for “Recovery energy system from thermal plant CT1” were completed
In week 27 of 2023, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) it has been completed the contract for supplying/design/execution/installing of the “Recovery energy system from thermal plant CT1” and his reception took place.
The contract goals were represented by three activities as follows:
Cod CPV: 42161000-5 – Activity 3.5 – Buffers/water tanks of 4000 liters with two coils
Cod CPV 42164000-6 – Activity 3.16 – Recovery thermic energy system (including design and installing)
Cod CPV: 45331100-7 – Activity 6.7 – Plumber works & auxiliaries in thermal plant (CT1) (buffers, recovery installation connection, circulation pumps, connections, valves)
The investment is part of the grant “Hybrid system for energetic efficiency using geothermal energy, applied in UPG”, financed by the EEA and Norwegian Financial Mechanisms 2014-2021 – “Energy Program in Romania”, Call 2 – Increased capacity for the supply of renewable energy – Geothermal energy.