Similar Posts
Thermal installations (including designing, execution and installing heat pumps and accessories)
In week 23 of 2023, in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) it was launched the public acquisition procedure SEAP for “Thermal installations (including designing, execution and installing heat pumps and accessories)”. The goals of public acquisition procedure SEAP launched are represented by eight activities as…
In week 8 of 2023, in the EEA Grant 107379/2019 the “Ground heat exchanger, design, execution and installation” works were finished.
In week 8 of 2023, in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) the “Ground heat exchanger, design, execution and installation” works were finished . The contract activities were completed as follows: Activity 6.11 – Geothermal heat exchanger installation works: heat exchanger location and installation, underground installation,…
In week 17 of 2024, in the Project EEA 107379/2019 the activities for automation system (system for command, measurement and control) (including design, execution and installing) (batch 1) were completed
In week 17 of 2024, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy applied in UPG Ploiesti campus) it has been completed the contract for supplying/design/execution/installing of the automation system (system for command, measurement and control) (including design, execution and installing) and his reception took place. The contract goals were…
In week 27 of 2023, in the Project EEA 107379/2019 the activities for “Recovery energy system from thermal plant CT1” were completed
In week 27 of 2023, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) it has been completed the contract for supplying/design/execution/installing of the “Recovery energy system from thermal plant CT1” and his reception took place. The contract goals were represented by three activities as follows: Cod CPV:…
“Drilling works”
Start In week 14 of 2022 in EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG), the tender winning company for contract Execution “Drilling works” took over the site and started the works. The signed contract goals were represent by four activities as follows: CPV code: 45262220-9 – Activity 3.13…
Groundworks and buried installations
In week 50 of 2022 in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) the procedure for SEAP public tender (SCN1111334/22.07.2022) was finished and the contract with the winner of the tender for the execution “Groundworks and buried installations” was signed. The contract goals are represent by five…