Thermal installations (fan convectors and auxiliary equipment, interior installation and insulation works) were completed
In week 9 of 2024, in the Project EEA 107379/2019 the activities for “Thermal installations (fan convectors and auxiliary equipment, interior installation and insulation works)” were completed
In week 9 of 2024, in the Grant EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus) it has been completed the contract for supplying/design/execution/installing of the “Thermal installations (fan convectors and auxiliary equipment, water buffers 25 m3, 3-way valves and automatic balancing valves, fan convector works and interior installations, interior pipes (additional), interior installation and insulation works)”.
The goals of the contract were represented by six activities as follows:
Code CPV: 42161000-5 – Activity 3.3 – purchase of water buffers of 25 m3;
Code CPV: 42130000-9 – Activity 3.7 – purchase of 3-way valves and automatic balancing valves;
Code CPV: 44621100-0 – Activity 3.9 – purchase of convectors and auxiliary equipment;
Code CPV: 45331100-7 – Activity 3.12 – purchase of convector works and interior installations;
Code CPV: 44160000-9 – Activity 3.17 – interior pipes (additional);
Code CPV: 45331100-7 – Activity 6.10 – interior installation and insulation works.
The investment is part of the grant EEA 107379/2019 “Hybrid system for energetic efficiency using geothermal energy, applied in UPG Ploiesti campus”, financed by the EEA and Norway Grants by Norwegian Financial Mechanisms 2014-2021 – “Energy Program in Romania”, Call 2 – Increased capacity for the supply of renewable energy – Geothermal energy.