In week 27 of 2023, in the Project EEA 107379/2019 the activities for “Recovery energy system from thermal plant CT1” were completed
In week 27 of 2023, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, applied in UPG) it has been completed the contract for supplying/design/execution/installing of the “Recovery energy system from thermal plant CT1” and his reception took place. The contract goals were represented by three activities as follows: Cod CPV:…
Startups in Romania – Open Call, Recording of Webinars and Presentations on How to Apply
The Open Call for Startups in Romania is an excellent opportunity for funding to your company and project idea. Innovation Norway has organised two webinars as well as a matchmaking for startups interested in applying for this call. You can see the recordings and presentations from these webinars here!
In week 16 of 2023, in the EEA Grant 107379/2019 the activities for “Groundworks and buried installation” were finished
In week 16 of 2023 in the EEA Grant 107379/2019 (Hybrid system for energetic efficiency using geothermal energy, it has been completed the contract for supplying/design/execution/installing of electric and hydronic external networks (“Groundworks and buried installations”) and his reception took place. The investment is part of the grant “Hybrid system for energetic efficiency using geothermal…
Workshop to promote geothermal hybrid energy project communication activities (Project EEA 2024/388116)
In May 28, 2024, at the Petroleum-Gas University of Ploiesti, Ap9 Hall, 9-12 hours, a workshop was held to promote by the Petroleum-Gas University of Ploiesti the project EEA 2019/107379 financed by EEA and Norway Grants and the Prahova County Council. In the project carried out within the Energy Programme in Romania and whose beneficiary…
In week 17 of 2024, in the Project EEA 107379/2019 the activities for automation system (system for command, measurement and control) (including design, execution and installing) (batch 1) were completed
In week 17 of 2024, in the project EEA 107379/2019 (Hybrid system for energetic efficiency using geothermal energy applied in UPG Ploiesti campus) it has been completed the contract for supplying/design/execution/installing of the automation system (system for command, measurement and control) (including design, execution and installing) and his reception took place. The contract goals were…
Workshop to promote geothermal hybrid energy project communication activities (Project EEA 2024/388116)
In May 29, 2024, at the Petroleum-Gas University of Ploiesti, Ap9 Hall, 9-12 hours, a workshop was held to promote by the Petroleum-Gas University of Ploiesti the project EEA 2019/107379 financed by EEA and Norway Grants and the Prahova County Council. In the project carried out within the Energy Programme in Romania and whose beneficiary…